Tawia Petroleum signs engineering, procurement and construction (EPC) contract for non-associated gas (NAG) compressor facility (NCF) station and remote gas dehydration unit (GDU) at Awari field by Q1 2024 It’s a schedule. According to sources.
“The request for proposal (RFP) for EPC services was issued on May 9, 2023, and the deadline for bid submission was September 10, 2023. The EPC contract is expected to be concluded by mid-January 2024.” said a project official. Details were shared with Zawya Projects.
The list of commercial bidders includes TDE Overseas ($281 million), Arabian International Contracting ($149 million) and Petrofac International Bahrain ($121.3 million). This was confirmed by officials from the three companies.
Tatweer Petroleum will install NAG Compressor Facility Stations (NCF), non-associated gas well connections, associated pipelines, and connections at compression and remote gas dehydration units (GDUs) to maintain gas supply capacity. We are engaged in gradual long-term field development. From the millet field.
The scope of work includes not only EPC but also supporting operational improvements at the Tawia oil facility.
The project is expected to be completed by the fourth quarter of 2029, officials said.
(Reporting by Senthil Palanisamy; Editing by Anoop Menon)